Gilman School Case Study

The prestigious Gilman School needed temporary space during renovation of its main building without sacrificing quality, budget, or detracting from the award winning architecture of their 68-acre Baltimore, Maryland campus.

The project needed to accommodate 385 students and support staff. The modular solution consisted of 35,000 square feet of temporary space for use as:

  • 24 Classrooms
  • 1 Library
  • 4 Conference rooms
  • Administrative offices
  • Food services facilities
  • Health station
  • Locker spaces

In order to complete the project, 48 air-conditioned modules previously utilized by the U.S. Naval Academy in nearby Annapolis, Maryland were brought to Gilman’s campus. USMGE facilitated the reuse of these existing buildings which minimized costs, reduced timelines, and decreased environmental impact.

Additional benefits to Gilman School were achieved by USMGE’s detailed and meticulous permit work with Baltimore City government officials.

Testimonials

What Our Clients Say About Us

"Thank you for working with Gilman School on this complicated project!"

“During the permit process with Baltimore City, USMGE was successful, often on short notice, to help Gilman resolve the issues with the City government. We were very pleased with the amount of time it took to have the buildings renovated and installed, on time and on budget.Overall we have found our relationship with USMGE...to be a rewarding and satisfactory experience. We would be pleased to recommend USMGE [to any potential customer]."”

- Sean T. Furlong, Director of Finance and Administration.
Recent Company News
April 26, 2026

When Modular Office Relocation Becomes a Strategic Upgrade

Turning an Office Move Into a Strategic Upgrade Moving a modular office does not have to be a headache. When…

Learn More
April 19, 2026

Relocation vs. Renovation for Modular Offices: Costs, Downtime, Permits

Choose the Smartest Path for Your Modular Office When a modular office no longer fits the way you work, you…

Learn More
April 12, 2026

Spring Site Readiness for Modular Relocation: Soil, Roads, and Utilities

Protect Your Spring Timeline with Smart Site Prep Spring is when many schools, healthcare providers, and public agencies try to…

Learn More